File Movement Timeline — Expanded View
Complete chronological record of all actions taken on this file
📅 26 October 2026
🟢 File Received at Sachivalay
P.S. Reddy, Chief Engineer (Roads), Gandhinagar
10:20 AM
File received from Circle Office (Superintending Engineer). Awaiting review and technical sanction.
🟢 Current Location
Pending review for 2 days
➡ Forwarded to Chief Engineer
S. Mukherjee, Superintending Engineer, Gandhinagar Circle
10:15 AM
All technical parameters verified as per IRC specifications. Budget allocation confirmed. Forwarding for CE technical sanction. DSC applied.
✅ Completed
🔑 DSC Signed
📝 Noting Added
S. Mukherjee, SE
10:00 AM
Technical review completed. Design parameters within acceptable limits per IRC:SP-6, IRC:SP-54. Bridge span: 4x30m PSC girder. Foundation: Well foundation, 12m depth. Soil BC: 18-22 T/sqm verified.
📅 24 October 2026
➡ Forwarded to Circle Office
D.K. Patel, Executive Engineer, Gandhinagar Division
03:50 PM
Reviewed feasibility report and budget estimates. All parameters within acceptable limits. Recommend forwarding for SE concurrence.
✅ Completed
🔑 DSC Signed
📝 Noting Added
D.K. Patel, EE
03:45 PM
Reviewed technical feasibility report and site plan. Budget verified under head 5054-00-796. Recommend forwarding to Circle Office.
📅 18 October 2026
📎 Rectification Submitted
V. Krishna Rao, Sub-Divisional Officer
02:00 PM
Geotechnical survey report from M/s Geo-Tech Labs (NABL Accredited) attached. Bore log data for all 8 pier locations included. Soil BC: 18-22 T/sqm. Foundation type: Well foundation recommended.
✅ Rectification Resolved
📅 12 October 2026
↩ Returned for Rectification
D.K. Patel, Executive Engineer
10:15 AM
Missing: Soil investigation / geotechnical survey report not attached. Required bore log data for all pier locations from NABL accredited agency.
↩ Returned
Resolved in 6 days
📅 08 October 2026
➡ Forwarded to Division Office
V. Krishna Rao, Sub-Divisional Officer
09:35 AM
Initial submission with site plan, preliminary estimate, and environmental clearance application. Forwarding for EE review.
📅 15 September 2026
📄 File Created
V. Krishna Rao, Sub-Divisional Officer, Gandhinagar Sub-Division
09:00 AM
New file created for National Highway-44 Expansion Bridge Phase-II. Initial documents uploaded: Site plan, preliminary estimate, project proposal, environmental clearance application.
📄 File Origin