Subject: Budget Verification for NH-44 Bridge Phase-II
I have reviewed the budget estimates submitted by the Division Office. The following observations are noted:
1. Budget Head: 5054-00-796-01-11 (NH Works) — Correct allocation as per FY 2026-27 budget.
2. Estimated Cost: ₹12.45 Cr — Within the sanctioned limit of ₹15 Cr for this project category.
3. Rate Analysis: Based on CPWD SoR 2026 — Verified. Non-schedule items have market rate justification attached.
4. Contingency: 3% provision included — Standard as per GR.
Recommendation: Financial parameters are within acceptable limits. May be forwarded for technical sanction.